MEP Retrofit Support
ACCO Mechanical
- Metro Commerce Bldg – HVAC Upgrades – Concrete Pads
Auburn Mechanical
- Sunrise Terrace – Plumbing Upgrades – Structural Support Below Floor, Ceiling Repairs, GWB Patch & Paint
- 1101 East Pike – Install Louvers In Existing Doors
- City of Pacific – Plumbing Upgrades
- Valley Regional Medical Center – Containment & Neg-air, Ceiling Repairs, GWB Patch & Paint
- City of Lacey – Plumbing Upgrades – GWB Patch & Paint
- Poly Clinic – Plumbing Upgrades – GWB Patch & Paint
- NW Hospital – Water Heater Replacement – Containment & Neg-air, Structural Support Above Ceiling, Ceiling Repairs, GWB Patch & Paint
- ICOS – Plumbing Upgrades – Concrete Patching
- Davis Wire – Plumbing Repairs – Exterior Siding Repairs & Painting
- Maple Elementary – Plumbing Upgrades – GWB Patch & Paint
- Fairmont school – Plumbing Upgrades – GWB Patch & Paint
- Peninsula – Plumbing Upgrades – GWB Patch & Paint
- Schmitz school – Plumbing Upgrades – GWB Patch & Paint
- Seattle University – Plumbing Upgrades – Concrete Cutting & Pour Back
- Best Western, Federal Way – Plumbing Upgrades – Concrete Cutting & Pour Back
- Albert Lee – Plumbing Upgrades – Concrete Cutting & Pour Back
- Plemmons Industries – Plumbing Upgrades – Concrete Pour Back
- Bio-Rad – Plumbing Upgrades – Containment & Neg-air, ACT Ceiling Repairs, GWB Patch & Paint
Enviromech
- Dynacare Labs – New AC Unit – Containment & Neg-air, Ceiling Repairs, GWB Patch & Paint
- Seattle Pacific University, McKenna Hall – HVAC Upgrade – Containment, Select Demo, ACT Ceiling Repairs, GWB Patch & Paint
Hermanson
- Group Health Annex – Plumbing Upgrades – Containment & Neg-air, GWB Patch & Paint, P-Lam Wainscot, Toilet Accessories
- Amgen – Fire Dampers Upgrades – Containment & Neg-air, Select Demo, GWB Patch & Paint, Fire Caulking
- Providence Everett Hospital – HVAC Upgrades – Containment & Neg-air, Select Demo, ACT Ceiling Repairs, GWB Patch & Paint, Flooring Repairs
- EEC Issaquah
McKinstry
- Westin Bldg – HVAC Upgrades & Condenser Water Expansion – Containment, Select Demo, Structural Demo & Upgrades, Roof Top Conc Demo & Pour Back, Ceiling Repairs, GWB Patch & Paint on 26 Flrs
- King County Jail, Seattle – Chiller Plant Replacement – Conc Cutting, Structural Supports, ACT Ceiling Repairs, GWB Patch & Paint
- Weyerhaeuser – HVAC Upgrades – ACT Ceiling Repairs, GWB Patch & Paint
- UW T Wing – HVAC RTU Replacement – Roof Curbs, Patch Roofing, Select Demo For Access, Install new Door & Frame
- World trade Center – HCAC Upgrades – Door replacement, Wall Covering Removal & Replacement, Subfloor Repairs & Flooring Repairs
- Microsoft Bldg 7 – Concrete Pads
- Financial Center – HVAC Upgrades – ACT Ceiling Repairs, GWB Patch & Paint
- 2 Union Square – Water Line Replacement – Containment, Select Demo, Ceiling Repairs, GWB Patch & Paint on 18 Flrs
CtR
- Pepsi Bottling Co, Seattle – Blower Mold Installation – Containment, Concrete Cutting, Removal & Excavation, Structural Concrete Pad, diamond Buffing & Sealing of Concrete, Structural Ceiling Supports For Piping, Roof Penetrations & Structural Supports, Re-route Roof Drains, Roof Patching, Add Floor Drains
Philips Medical
- Valley Medical Center – Primary Care X-Ray Installation – Containment & Neg-air, Elect RI, GWB Patch & Paint, Flooring Repairs
Pride Electric
- Puget Sound Blood Center, UDL – Generator Pad
- Bastyr University – Equipment Pad
SASCO Electric
- Alderwood Mall – Kiosk Relocations – Overnight Jobs (10pm – 8am), Concrete Cutting, Trenching & Pour Back, Ceramic Tile Repairs
Snyder Roofing
- Redmond Business Park – Reroof Project – Select Demo of Roof Structure & Rebuild, Replace & Paint Fascia Boards
Titan Electric
- UW Data Center – UPS Replacement – Structural Upgrades At Floor Penetrations, Build Utility Chase, ACT Ceiling Repairs, GWB Patch & Paint, Flooring Repairs
University Mechanical
- Granit Falls High School RTU Replacements – RTU Curbs & Structural Upgrades, Roofing replacement & Repairs, Select Demo, ACT Ceiling Repairs, GWB Patch & Paint, Concrete Pad, Gas Line Supports